The City of Show Low is preparing for a key decision on its major facility project later this month.

Project Background

The Sports and Events Center, estimated at $56.8 million, has progressed through design phases with initial site work authorized earlier in the year.

Upcoming Decision

A second and final guaranteed maximum price contract amendment is tentatively scheduled for council consideration on November 17. This step would address the remaining construction elements following the first GMP approval of $4,164,680 for mobilization, access road, mass grading, and steel down payment.

Public Works Director Shane Hemesath has noted that costs have increased since the project's inception.1