The City of Flagstaff continued its Road Repair and Street Safety program with notable progress reported in early June. On Aztec Street, contractors completed concrete removal during the week leading up to the June 5 update, while subcontractors handled various tasks across the project sites.
Utility and Concrete Work
Utility lowering operations began on Wednesday, June 3, and were scheduled to continue through June 12. Concrete work remained active on Circle View, Clearview, and Canyon View streets through June, alongside targeted segments on Aztec Street from May 26 to June 19.
Additional Street Schedules
Further work included Switzer Canyon Drive and Columbus Avenue from June 3 to June 19, Coy Drive from June 8 to June 26, and Dolores Lane set to start June 15 and run through July 3. These activities form part of the broader Phase 1 efforts addressing pavement and safety improvements citywide.
Intermittent traffic impacts, including short delays, have been noted on affected routes as construction proceeds. The program, funded by a dedicated sales tax, focuses on crack sealing, overlays, and related infrastructure updates.
Upcoming phases in late June will shift focus to additional streets, with crews expected to maintain schedules amid the summer season. The content of this article was computed by analyzing available sources.